Lancair Evolution Build Shop Task List
Week 1
- Prepare and close wings
- Prepare and close elevators
- Prepare and close horizontal stabilizer
- Install wing wiring harness
- Assemble & install landing gear
- Fabricate & install wing hydraulics
- Fabricate & install wing fuel system
- Fabricate & install wing brake system
- Install navigation lights
- Assemble & install flap hardware and controls in wing
- Assemble & install aileron in wing
Wing, flaps, ailerons, horizontal stabilizer, and elevators are ready for body work and paint.
Week 2
- Prepare and close rudder
- Install horizontal stabilizer to fuselage
- Install rudder controls
- Install elevator & aileron controls in fuselage
- Assemble baggage door
- Install baggage door
- Assemble main door
- Install main door
- Prep co-pilot & passenger windows
- Install windows
- Install tail cap
Fuselage is ready for body work firewall aft.
|
|
|
|
|
|
|
 |
|
|
|
|
Home | Explore Lancair | Our Aircraft | News | Support | Merchandise | Contact
Lancair International Inc. 2244 Airport Way, Redmond, Oregon 97756 (541) 923-2244
Copyright © 2007 Neico Aviation Inc. All rights reserved, specifications and pricing to change without notice.
Lancair, the Lancair logo, Lancair IV-P, Lancair PropJet, Lancair Legacy, Lancair Legacy FG and Lancair ES are
trademarks of Lancair International Inc. and Neico Aviation Inc. No images or content in their part or entirety
may be used without the expressed permission from Lancair International Inc. and Neico Aviation Inc.
|
|
|
|